SC
Sample Client
Locate Agent  ·  811
POWERED BY ALVATES AI
Total Locate Tickets
0
No tickets yet
Dig-Clear Segments
0
Pending ticket submissions
Non-Responses
0
No escalations required
Expiring ≤ 5 Days
0
No tickets expiring
Avg Utility Response
utilities responded
Ticket Dashboard
Bore Path Map
Submit New Ticket
State Compliance
Ticket Dashboard 22 tickets
Ticket # Segment / Location State Work Type Submitted Expires Utilities Status Dig Clear
#TX-78190
I-30 Bore Shot — Fort Worth to Arlington
Ticket Info
State / CenterTexas — Texas 811 (TESS)
Work TypeHDD
Depth6 ft minimum
Bore Length1,400 ft
SubmittedMay 5, 2026 08:42
ExpiresMay 26, 2026 (12 days)
ROW PermitTxDOT-26-8819
NTIA SegmentTX-BEAD-W07
Dig Clear⛔ HOLD — Non-Response
Utility Responses (6 of 7)
Oncor Electric Delivery
Marked
Fort Worth Water Dept
Clear — No Conflict
AT&T Texas
Marked
Charter / Spectrum TX
Clear — No Conflict
Comcast / Xfinity
Clear — No Conflict
TxDOT Fiber Infrastructure
Clear — No Conflict
Atmos Energy
⚠ No Response — 34hrs
AI-Generated Narrative
Contractor proposes to install fiber optic conduit via horizontal directional drill (HDD) beginning at I-30 eastbound near MP 22.4 at the Hulen St interchange, drilling east toward Fielder Rd, approximately 1,400 linear feet at minimum 6ft depth within TxDOT ROW (Permit TxDOT-26-8819). Bore path is 10ft south of existing pavement edge. Crew contact on-site throughout locate window.
Ticket Timeline
Ticket Submitted to Texas 811
May 5, 2026 08:42 · #TX-78190
2-Business-Day Legal Window Opens
May 7, 2026 08:42
!
Atmos Energy Non-Response
34hrs elapsed — escalation required
Dig-Clear Issued to Foreman
Awaiting full utility response
Ticket Expires
May 26, 2026 — auto-renewal queued